Hyderabad Metro Extension: Construction Update
As of October 2026, main construction on the Hyderabad Metro Phase 2 extension has not started. In May 2026, the Centre gave in-principle support with 50:50 funding. Final approval now depends on its review of the project report. Early work is under way only on the Old City line, where road widening continues. The state also bought out L&T's stake in Phase 1 in April 2026, which cleared a key hurdle. For Kismatpur, the nearest planned line runs from Raidurg to Kokapet. Current plans show no station in Kismatpur itself.
This page explains where each part stands, what comes next and what it means for buyers.
Hyderabad Metro Phase 2 Status in October 2026
| Milestone | Date | Status |
|---|---|---|
| State cabinet approves Phase 2 plan | October 2024 | Done |
| State grants administrative sanction | November 2024 | Done |
| State takes over Phase 1 from L&T | 29 to 30 April 2026 | Done, for about ₹15,000 crore |
| Chief Minister seeks central approval | 6 May 2026 | Done, 122.9 km plan at ₹38,595 crore |
| Centre gives in-principle support, 50:50 funding | 20 to 21 May 2026 | Done |
| Final central approval after DPR review | Pending | Awaited |
| Main civil works on new corridors | Not started | Awaited |
| Old City corridor road widening | Ongoing | Property acquisition and pillar marking |
The Planned Phase 2 Corridors
The plan has changed in size a few times. The latest submission covers about 122.9 km of new lines. Reports on the Centre's in-principle nod mention about 162 km when the later Phase 2B corridors are included.
| Corridor | Approximate Length | Area Served |
|---|---|---|
| Nagole to Rajiv Gandhi International Airport | About 36.6 km | East and south Hyderabad to the airport |
| Raidurg to Kokapet Neopolis | About 8 to 11.6 km | Financial District and Kokapet |
| MGBS to Chandrayangutta (Old City) | About 7.5 km | Old City |
| Miyapur to Patancheru | About 13.4 km | North-west industrial belt |
| LB Nagar to Hayathnagar | About 7.1 km | East Hyderabad |
| JBS to Medchal and Shamirpet | Phase 2B | North Hyderabad |
| Airport to Future City | Phase 2B | South, towards the new city area |
*Lengths vary across plan versions. Final routes depend on central approval.
What Has Moved on the Ground
The only visible work so far sits on the Old City corridor. The metro team has pushed road widening between MGBS and Chandrayangutta. Officials earlier said about 1,100 properties would be affected, and they later reduced that number. Pillar marking has begun along parts of the route. Design changes help protect old heritage buildings.
On the other lines, work is still at the planning stage.
What Comes Next
- The Centre completes its review of the detailed project report.
- The Union Cabinet gives final approval for the project.
- The state and Centre set up the funding and a joint company, if required.
- Tenders go out for civil works, corridor by corridor.
- Construction begins, usually starting with priority corridors.
Most metro projects in India take four to six years from the start of works to opening. So new Phase 2 lines are unlikely to open before about 2030.
What It Means for Kismatpur
Kismatpur does not have a metro station today. The nearest working stations sit about 17 km away. Current plans do not show a station in Kismatpur itself.
Two planned corridors could still help residents:
- Raidurg to Kokapet Neopolis: would bring the metro closer to the Financial District and Kokapet.
- Nagole to the airport: would link the airport with the east of the city, far from Kismatpur.
For now, treat metro access as a long-term plus for Kismatpur, not a reason to buy today.
Why Phase 2 Took Time
Several issues slowed the Phase 2 plan between 2024 and 2026. The Centre first raised questions about the public-private model used for Phase 1. The state then bought out L&T's stake in Phase 1, which settled that concern. The plan also grew from about 76 km to over 120 km as new routes were added. Each change meant fresh studies and a revised project report.
With the funding model now agreed in principle, the main step left is final central approval. After that, tenders and construction can begin.
How Kismatpur Residents Travel Today
| Mode | What Is Available |
|---|---|
| Car or cab | ORR about 4 to 6 km away, plus Narsingi side roads |
| Bus | TGSRTC services along NH-163 and towards Mehdipatnam |
| Suburban rail | Shivrampally and Budvel stations, about 10 to 12 km away |
| Metro | Nearest stations about 17 km away |
Homes in Kismatpur and the Metro Timeline
Buyers looking at new projects in Kismatpur should plan around road access first. SOBHA's upcoming Sobha Amara at Kismatpur expects possession in December 2029. By then, the road upgrades should be ready, while metro lines may still be under construction. The project plans 816 homes in two G+56 towers, with the 2 BHK from an indicative ₹1.61 Cr*.
*Indicative pricing, subject to change and developer confirmation.
Frequently Asked Questions about the Hyderabad Metro Extension
Main construction has not started as of October 2026. Only Old City road widening is under way.
The Centre gave in-principle support with 50:50 funding in May 2026. Final approval awaits its review of the project report.
The latest submission covers about 122.9 km. Reports mention about 162 km when Phase 2B corridors are included.
Current plans do not show a station in Kismatpur. The nearest planned corridor runs from Raidurg to Kokapet.
No firm date exists yet. New lines are unlikely to open before about 2030.
A Nagole to airport corridor is part of Phase 2. It awaits final approval and construction.