Chevella Road infrastructure pipeline 2026-2030
The Chevella Road pipeline for 2026 to 2030 centres on the ₹900 crore four-laning of NH-163. This 46 km stretch runs from Appa Junction to Manneguda, and officials target completion around late 2027. Bypasses at Moinabad and Chevella add to it. So do a ₹161 crore Kismatpur road widening and new Musi link roads. Beyond 2027, the metro, the Regional Ring Road and a data centre city could reshape the corridor. Together, these projects should cut travel times and lift land values along the road.
This page lists every major project, its status and timing, and what it means for buyers.
Chevella Road Infrastructure Projects at a Glance
| Project | Key Facts | Status in 2026 | Expected Timing |
|---|---|---|---|
| NH-163 four-laning | 46 km, Appa Junction to Manneguda, about ₹900 crore | Under construction, round-the-clock work | Around late 2027 |
| Moinabad bypass | About 4.8 km, 60 metres wide | Under construction | With the four-laning |
| Chevella bypass | About 6 km, Kesaram towards Ibrahimpally | Under construction | With the four-laning |
| Underpasses at busy crossings | Vehicle and light vehicle underpasses | Under construction | With the four-laning |
| Bandlaguda Jagir to Kismatpur road | About 30 to 100 feet, ₹161 crore | Moved to HACL in August 2026 | 2027 to 2028 |
| Musi corridor link roads | Seven roads incl. Kismatpur Bridge to Budvel layout | Proposed | 2027 onwards |
| Hyderabad Metro Phase 2 | Plan sent to the Centre on 6 May 2026 | Awaiting central approval | 2028 to 2030 and beyond |
| Southern Regional Ring Road | Planned route via Chevella and Shankarpally | Planning stage | 2028 onwards |
| Data centre city, Aloor | 1,500 acres in Chevella mandal | Detailed report ordered | 2027 onwards |
*Timelines are estimates based on official statements and news reports. They can change.
1. NH-163 Four-Laning: Appa Junction to Manneguda
This is the biggest project on Chevella Road. The 46 km stretch is being widened from a narrow two-lane road to four lanes. The Union road transport ministry sanctioned about ₹900 crore for the work.
The project stalled for years over the old banyan trees along the route. On 31 October 2025, the National Green Tribunal approved a revised design with environmental conditions. About 765 of 915 banyans stay in place, and around 150 move within the corridor. After a bus crash near Mirjaguda killed 19 people in November 2025, the state pushed the work forward. Crews now work in two shifts round the clock.
What it means for you: safer, faster trips between Kismatpur and Chevella, and stronger land values.
2. Moinabad and Chevella Bypasses
Two bypasses will take highway traffic out of busy town centres. The Moinabad bypass runs about 4.8 km and is about 60 metres wide. The Chevella bypass runs about 6 km, from Kesaram towards Ibrahimpally. Both form part of the four-laning package.
What it means for you: fewer jams in Moinabad and Chevella, and new plot demand near the bypasses.
3. Bandlaguda Jagir to Kismatpur Road Widening
This road links the Kismatpur end of Chevella Road to the city side. The plan widens it from about 30 feet to 100 feet at a cost of ₹161 crore. In August 2026, the state moved the job to a new agency, HACL.
What it means for you: faster access from Kismatpur towards Rajendranagar, Attapur and the old city side.
4. Musi Corridor Link Roads and Bridges
The Musi Riverfront Development Corporation has proposed seven new roads to connect the ORR with the Musi corridor. One planned link runs from Kismatpur Bridge to the HMDA Budvel layout. Earlier plans also included a high-level bridge linking the Inner Ring Road and Kismatpur road at Bandlaguda Jagir.
What it means for you: more routes in and out of Kismatpur, and less load on one road.
5. Hyderabad Metro Phase 2
On 6 May 2026, the state sent its Metro Phase 2 plan to the Centre for approval. The provisional plan covers about 122.9 km. As per Sobha Amara project details, a metro station is planned about 2 km from the Kismatpur site. Final routes and stations still await central approval.
What it means for you: a possible metro link near Kismatpur later this decade. Treat it as a future plus, not a certainty.
6. Southern Regional Ring Road
The Regional Ring Road will form an outer ring around Hyderabad. Its southern half is planned to pass through the Chevella and Shankarpally belt. Land acquisition and approvals are still in progress.
What it means for you: better links from the outer Chevella belt to other highways and growth areas.
7. Data Centre City at Aloor
In June 2026, the state picked 1,500 acres at Aloor in Chevella mandal for a data centre city. The Chief Minister asked officials to prepare a detailed report.
What it means for you: if it goes ahead, it could bring jobs to the outer belt.
Year-by-Year Outlook
| Year | What to Expect |
|---|---|
| 2026 | Four-laning and bypass works in full swing, Kismatpur road shifted to HACL |
| 2027 | Four-lane NH-163 targeted to open, bypasses complete |
| 2028 | Kismatpur road widening and Musi link roads progress |
| 2029 | Branded high-rises at the Kismatpur end begin handover |
| 2030 | Metro Phase 2 and Regional Ring Road works may advance |
How the Pipeline Lines Up With New Homes
For buyers at the Kismatpur end, the timing works well. Most road works should finish before new projects hand over. SOBHA's upcoming Sobha Amara at Kismatpur expects possession in December 2029. By then, the four-lane NH-163 and the wider Kismatpur road should both be ready. The project plans 816 homes in two G+56 towers, with the 2 BHK from an indicative ₹1.61 Cr*.
*Indicative pricing, subject to change and developer confirmation.
Frequently Asked Questions about Chevella Road Infrastructure
Officials target completion of the 46 km four-lane road around late 2027.
The Union road transport ministry sanctioned about ₹900 crore for the Appa Junction to Manneguda stretch.
The Metro Phase 2 plan awaits central approval. Project details show a station planned about 2 km from Kismatpur.
Yes, the southern half of the Regional Ring Road is planned through the Chevella and Shankarpally belt.
The state has picked 1,500 acres at Aloor in Chevella mandal for a proposed data centre city. A detailed report is under preparation.
Better roads and new jobs usually lift land values. Prices still depend on project timelines and market conditions.